Thread 14: How do you estimate time for a project when you use AI Code?
Platform
Link
Full Post Text (Key Excerpt)
“In a new outsourcing role, I am pressured by delivery timelines and trying to estimate project time when AI coding speed varies and uncertainty is high.”
Why This Matches Ryva ICP
Timeline confidence under AI-assisted execution is a current operator pain for small teams shipping under client pressure.
Underlying Problem
Teams estimate output speed but fail to budget for review, integration, and rework, creating repeated deadline misses.
Suggested Public Reply (Copy)
Treat AI output as draft velocity, not done velocity. Estimate in three buckets: generation, verification, and integration. Most slips happen when teams budget only generation and ignore review + edge-case rework.